The project board for long jobs

A job that ships a floor or a building at a time gets one easy picture: every phase on a line of time, and a tile for each phase. It is not a scheduling program. The only date you keep is the day the site needs each phase.

Open it

  1. Click Jobs.
  2. Click Projects, next to Board, List, Stations and Calendar.

What you see

  • One card for each job that is split into phases.
  • A line of time across the card, with the months, a mark for Today, and a dot for each phase on the day the site needs it.
  • A tile for each phase: its name, what is in it, the day it is needed, and five marks for its steps: not released, released, in production, delivered, installed.
  • Green: installed. Blue: on track. Amber: the day is close and the phase is a step behind. Red: the day has passed and it is not delivered. Amber and red tiles say why in plain words.
  • Four numbers at the top. Click any of them to see the phases behind it.

Split a job into phases

  1. Open the job.
  2. Under Project details, click Add a phase.
  3. Type the phase, like Level 2 exam rooms. To add several at once, put commas between them.
  4. Type what is in it.
  5. Pick the day the site needs it.
  6. Click Add it.

Keep it current

  • When a phase moves a step, pick the new step in the box on its tile. That is the only upkeep.
  • If the site's day moves, click Change on the tile and pick the new day. The change is written on the job's timeline.

When amber shows A phase turns amber when it is not released with 21 days to go, or released and not in production with 10 days to go. Change both numbers in Settings, Capacity, The project board.

Also

  • The Radar lists a job with a late phase, or one close and a step behind.
  • The job page still has the same phases under Project details, with a link to the board.